Compare the two displayed Deye modular C&I ESS solution pages

Open the exact architecture page for source-derived modules and claims, then confirm the released one-line, model revisions, cluster/PCS ratio, included scope, studies, documents, delivery, commissioning and commercial obligations.

Displayed solution architectures

Separate STS-backed and AC-DC modular routes

The two pages use different conversion and transfer concepts. Their switching, overload, PV, battery and included-equipment statements must remain tied to the exact source configuration.

PCS + MPPT + STS route

The displayed concept references 100/125 kW PCS, a 200 kW MPPT module and 500 kW STS. Confirm the approved one-line, STS topology/rating, backed bus, bypass, protection and transfer conditions.

PCS + MPPT + AC-DC route

The second concept references 100/125 kW PCS, 200/250 kW MPPT and 80 kW AC-DC. Confirm DC- and AC-coupled paths, retrofit intent, auxiliary supply, transfer architecture and exact modules.

257 kWh battery-cluster building block

Source pages reference BOS-B Pro-A3 257 kWh clusters and modular expansion. Verify exact battery revision, usable energy, voltage/current, BMS, permitted cluster count, enclosure and fire/thermal scope.

100 kW to 2.5 MW project scaling

A source scaling range is not a released project design. PCS quantity, AC bus, transformer, protection, fault level, battery ratio, EMS, redundancy, layout and commissioning require engineering.

C&I ESS project checks

Six workstreams before requesting a modular C&I ESS quotation

A bankable request defines operating objectives, power/energy, topology, site interfaces, safety and contractual scope before selecting modules.

Use case and operating modes

State backup, peak shaving, demand management, self-consumption, zero export, microgrid or another objective plus load profile, critical bus, outage behavior and control priority.

Power, energy and duration

Provide kW, kWh and required duration with load/dispatch assumptions, usable SoC window, losses, temperature, degradation, reserve, overload and future expansion basis.

PV, PCS and coupling topology

Provide PV/MPPT or AC-coupled design, existing equipment, DC and AC voltages, PCS quantity, common bus, AC-DC modules, STS/bypass and generator/grid interfaces.

Battery, BMS and EMS hierarchy

Confirm exact cluster model/revision, quantity, voltage/current, BMS levels, communications, PCS pairing, EMS functions, meters/CTs, SCADA and cybersecurity/access responsibilities.

Grid, switchgear and site engineering

Define transformer, MV/LV switchgear, protection/selectivity, earthing, fault level, grid studies, fire strategy, HVAC, auxiliaries, civil works, layout, access and authority route.

Documents, delivery and commissioning

Request approved one-line/BOM, calculations/studies scope, exact manuals/certificates, FAT/SAT, packing/phasing, installation, commissioning, training, warranty, service, spares and exclusions.

Integration and contract boundaries

A modular solution page is not a complete EPC or performance guarantee

Final capability depends on the released combination, project design, site, controls, grid and contracted supply/services. Keep every scope boundary explicit.

Architecture labels are not included scope

PCS, MPPT, STS, AC-DC, batteries, EMS, switchgear, transformer, HVAC/fire, auxiliaries and civil works must each be marked included, optional, excluded or supplied by others.

Transfer and overload claims are exact-route evidence

Any 0 ms, under-10 ms or short-duration overload statement applies only to the named topology, load conditions, battery/DC capability, settings, test basis and released configuration.

Cluster count does not guarantee project performance

Energy, duration, power, efficiency, cycle life and availability depend on SoC window, C-rate, temperature, losses, degradation, controls, redundancy and warranty conditions.

Fire features are not site approval

Cell chemistry or module-level aerosol statements do not replace project hazard analysis, detection/suppression design, ventilation, separation, egress, emergency response and authority acceptance.

Continue the project review

Connect modular ESS architecture to C&I operating objectives

Use the hybrid solution to define the site case, then use the sizing guide to document kW, kWh, duration and reserve assumptions.

Deye modular C&I ESS FAQ

Questions to close before selecting a C&I ESS architecture

These answers support procurement; final electrical, battery, controls, fire, civil, grid and commissioning decisions remain project-specific.

What is the difference between the two displayed Deye modular C&I ESS routes?

One source page describes 100/125 kW PCS with a 200 kW MPPT module and 500 kW STS; the other describes 100/125 kW PCS with 200/250 kW MPPT and an 80 kW AC-DC module. Confirm the exact one-line, transfer/coupling intent, modules and project scope rather than treating them as variants of one SKU.

Does the 100 kW–2.5 MW label define a complete system size?

No. It is a displayed modular solution range. Final PCS quantity, battery clusters, duration, PV/AC coupling, bus/transformer, fault and protection design, controls, redundancy, site layout and grid approval must be engineered and released for the project.

Does a 257 kWh battery cluster provide 257 kWh of usable project energy?

Not necessarily. Confirm nominal versus usable energy, SoC window, current/C-rate, temperature, auxiliaries, conversion losses, degradation, reserve, warranty and control limits for the exact cluster and system configuration.

What should a Deye modular C&I ESS RFQ include?

Include load/dispatch profile, backup or grid objective, kW/kWh/duration, PV and AC topology, voltage/transformer, STS/AC-DC/PCS/cluster concept, EMS/SCADA, protection/grid studies, fire/civil/site scope, documents, FAT/SAT, commissioning, service and delivery phasing.

Deye modular C&I ESS procurement

Deye Modular C&I ESS Concepts for Hybrid and Backup Projects

Compare two displayed 100 kW–2.5 MW C&I ESS solution pages. Both source concepts reference 100/125 kW PCS and 257 kWh BOS-B Pro-A3 battery clusters, while one route describes 200 kW MPPT plus 500 kW STS and the other describes 200/250 kW MPPT plus 80 kW AC-DC. These are modular solution architectures, not one fixed turnkey SKU. Confirm load mode, PV/AC coupling, battery clusters, switching, EMS, fire strategy, switchgear, transformer, civil scope, grid studies, commissioning and contractual boundaries.

Prepare a Deye modular C&I ESS RFQ by operating architecture

Send the load and modes, kW/kWh/duration, PV/AC coupling, voltage and grid, PCS/MPPT/STS or AC-DC concept, battery/EMS, site/fire/civil scope, documents, commissioning and delivery plan.

Build Deye C&I ESS RFQ
Chat with Us